Building Consent vs Resource Consent: What’s the Difference?

Building consent and resource consent are often talked about together, but they deal with different parts of a development project.

In simple terms:

  • Building consent focuses on whether the proposed building work will comply with the Building Code.

  • Resource consent focuses on whether the proposed activity or development is allowed under the relevant planning rules and how its effects are managed.

A project may need one, both or, in some cases, neither. Understanding the difference early makes it much easier to work out which approvals need to be addressed.

What Is Building Consent?

A building consent is approval to carry out specific building work in accordance with the approved plans and specifications.

Council assesses the proposed work against the New Zealand Building Code. All building work must comply with the Building Code, although some lower-risk work is exempt from needing a building consent.

Building consent can become relevant for work such as structural alterations, additions, new buildings and certain demolition or other construction work.

The focus is mainly on how the building will be designed and constructed.

What Is Resource Consent?

A resource consent deals with activities that are not permitted as of right under the relevant district or regional planning rules.

This can include matters such as:

  • land use and subdivision

  • building location, height or scale

  • earthworks

  • use of land for a particular activity

  • effects involving water, discharges or coastal areas

The exact requirements depend on the proposal and the planning provisions applying to the site.

The focus is therefore less on how the building itself is constructed and more on whether the proposed development or activity is appropriate in that location and how its effects are addressed.

How Are the Two Different?

A useful way to think about the difference is:

Building Consent

Resource Consent

Assesses building work

Assesses land use and environmental effects

Based on the Building Act and Building Code

Based on planning provisions and resource management legislation

Looks at how work will be constructed

Looks at what is proposed, where it is proposed and its effects

May be required for new buildings or alterations

May be required where planning rules are not met or an activity requires consent

Follows its own council approval process

Follows a separate resource consent process

The two approvals are separate. Official guidance specifically notes that building consents follow a different process from resource consents.

Can a Project Need Both?

Yes, and this is common.

Imagine a new building is proposed on a property.

The resource consent process might assess matters such as the building's height, position, site coverage or effects on surrounding properties.

The building consent process would then assess matters such as the structural design and compliance with the Building Code.

The same project is being considered, but each approval is looking at it through a different lens.

One approval does not replace the other.

Can You Need Building Consent but Not Resource Consent?

Yes.

A project might comply fully with the relevant district and regional planning rules but still involve building work that requires building consent.

For example, an addition could potentially meet all relevant planning standards while still requiring approval under the Building Act.

Likewise, Building Performance guidance notes that building consent may be required even where resource consent is not.

This is why complying with the district plan does not automatically mean construction can begin.

Can You Need Resource Consent but Not Building Consent?

This can also happen.

Resource consent may be triggered by the use of land or an activity, even where little or no consented building work is involved.

Examples could include subdivision, particular land uses, earthworks or activities involving water or discharges. Resource consent requirements depend on the relevant district or regional plan rather than simply on whether a building is being constructed.

The two approval pathways therefore need to be checked independently.

Which Consent Should Come First?

There is no single answer that applies to every project.

The two processes can interact, so the best sequence depends on what is proposed and the issues involved.

For some projects, it makes sense to resolve important planning matters before investing heavily in detailed building design. If resource consent could significantly affect the building's size, position or layout, obtaining greater planning certainty first may avoid designing a building around assumptions that later need to change.

On other projects, information for both processes may be developed alongside each other.

The key is understanding which planning and building requirements could influence the design before the project becomes too advanced.

Why Doesn't One Consent Automatically Cover the Other?

Because each approval answers a different question.

A building consent essentially asks:

Will this building work comply with the Building Code if it is completed in accordance with the approved plans?

A resource consent asks:

Can this activity or development proceed under the relevant planning framework, and how should its effects be addressed?

Receiving approval under one system therefore does not confirm compliance with the other.

Even if resource consent is not needed, building consent may still be required. Likewise, receiving building consent does not remove any separate obligation to obtain resource consent.

What Should Be Checked at the Start of a Project?

Before progressing too far with a design, it is worth establishing:

  • whether the planning rules trigger resource consent

  • whether the proposed building work requires building consent

  • whether one approval could influence the information needed for the other

  • whether other project approvals or technical investigations may also be required

This provides a much clearer picture of the overall approval pathway rather than treating each consent as an isolated task.

Understanding Which Approvals Your Project Needs

Building consent and resource consent serve different purposes, but they often need to work alongside each other on the same development.

Civix can review the planning requirements for a project and assist with both resource consent and building consent considerations, helping the wider project team understand how the approvals fit into the development process.

Related Guides VIEW ALL

What Planning Checks Should You Make Before Buying or Developing a Site?

A property can look perfect for a development on paper. It might be in the right location, have plenty of space and appear suitable for what you have planned.

READ MORE  

How Do District Plan Rules Affect What You Can Build on a Property?

Two properties can look almost identical but have very different development potential.

READ MORE  

What Happens During the Resource Consent Process in New Zealand?

Finding out that a project needs resource consent is only the beginning.

READ MORE  

What Can Make a Development More Difficult to Consent?

Some developments move through the planning process relatively smoothly. Others require more investigation, supporting reports, consultation or changes to the design before consent can be granted.

READ MORE  

Understanding Earthworks: What Your Project May Need and How to Get Started

Earthworks are often one of the first major stages of a subdivision or land development project. They involve reshaping the existing ground so the site can support buildings, accessways and other future construction.

READ MORE  

From Design to Approval: Understanding the Engineering Approval Process

Engineering approval is the stage where detailed civil plans are reviewed before construction begins. It is commonly required for subdivisions and developments involving earthworks, roads, accessways, drainage or connections to public infrastructure.

READ MORE  

Understanding Flood Risk: Overland Flow Paths, Flood Modelling and Site Constraints

Flood-related constraints can affect where buildings are placed, how high finished floor levels need to be and how stormwater is managed across a development site.

READ MORE  

Planning Safe and Practical Access: Roads, Driveways and Vehicle Movement

Access design affects how safely and easily vehicles can enter, leave and move around a property. It can also influence the wider layout of a subdivision or development, including building placement, earthworks and service connections.

READ MORE  

Site Services Explained: Water, Wastewater and Stormwater for New Developments

Site services are the systems that allow a development to connect with essential infrastructure. For most subdivision and land development projects, this includes water supply, wastewater disposal and stormwater management.

READ MORE  

Erosion & Sediment Control Guide

Earthworks can significantly change the way water moves across a development site. Once vegetation is cleared or soil is exposed, rainfall can loosen and carry sediment into stormwater networks, neighbouring properties, streams and other receiving environments.

READ MORE  

Overland Flow Paths & Flood Risk Guide

Flood risk is not always obvious when looking at a property. A site may remain dry in normal conditions but still sit within a flood-prone area or carry significant surface water during heavy rainfall.

READ MORE  

Stormwater Treatment Design Guide

Stormwater treatment is an important part of many subdivision, land development and infrastructure projects. As sites are developed, buildings, roads, car parks and other hard surfaces can increase the volume and speed of runoff while also changing the types of contaminants entering the stormwater system.

READ MORE  

On-Site Stormwater Management Guide

Development usually increases the amount of hard surface on a property. Roofs, driveways, roads and paved areas prevent rainfall from soaking naturally into the ground, which can increase the volume and speed of stormwater runoff.

READ MORE  

Chemical Treatment for Earthworks Guide

Earthworks can produce sediment-laden runoff when exposed soil is disturbed by rainfall. Standard erosion and sediment controls are often used to slow this water and allow suspended soil particles to settle before discharge.

READ MORE  

Building Consent vs Resource Consent: What’s the Difference?

Building consent and resource consent are often talked about together, but they deal with different parts of a development project.