What Happens During the Resource Consent Process in New Zealand?

Finding out that a project needs resource consent is only the beginning.

Before an application reaches council, the proposal needs to be understood, the relevant planning rules identified and the supporting information prepared. From there, the application moves through council assessment, with the exact pathway depending on the project.

At a high level, the process looks something like this:

  1. Understand the proposal

  2. Check the planning rules

  3. Prepare the application

  4. Lodge with council

  5. Council assessment

  6. Further information or notification, if required

  7. Decision

  8. Consent conditions

Not every project will follow exactly the same path, but understanding these stages makes the process much easier to navigate.

1. Start With the Proposal and Planning Rules

Before preparing a resource consent application, the first job is to establish exactly why consent is required.

This means comparing the proposed development with the relevant district or regional planning provisions. The assessment identifies which rules are triggered, how the activity is classified and what matters will need to be addressed in the application.

This stage can also influence the design. If a particular part of the proposal creates a planning issue, the project team can consider whether it makes sense to alter the design or address that matter through the consent application.

2. Prepare the Resource Consent Application

Once the planning pathway is understood, the application can be put together.

The information required will depend on the project, but an application may include:

  • plans and a clear description of the proposed development

  • an assessment against the relevant planning provisions

  • an Assessment of Environmental Effects

  • supporting reports or technical information where required

A straightforward land use proposal may need relatively limited supporting information, while a larger or more complex development could involve several technical disciplines.

The application needs to give the council enough information to understand both what is proposed and the effects it may create.

3. What Does the AEE Cover?

The Assessment of Environmental Effects, usually referred to as an AEE, is an important part of the application.

It considers the actual and potential environmental effects of the proposal and explains how adverse effects will be avoided, remedied or mitigated where relevant.

The amount of detail should reflect the scale and significance of the effects involved. A small proposal and a major development should not require the same level of assessment.

Depending on the project, the AEE may draw on information from engineers, surveyors, environmental specialists or other technical experts.

4. The Application Is Lodged With Council

Once the application is ready, it is submitted to the relevant consent authority.

Council then checks the application before progressing its assessment. If required information is missing, the application may need to be completed before it can move forward.

Once accepted, the application moves into formal processing.

  1. Application lodged

  2. Council checks the information

  3. Planner assesses the proposal

This is where the planning assessment, AEE, plans and supporting reports are considered together.

5. Council May Ask for More Information

During its assessment, the council may decide it needs more information before it can continue processing the application.

This is commonly referred to as a request for further information, or RFI.

An RFI could ask for clarification of part of the proposal, amendments to plans, further explanation of an environmental effect or additional technical information.

It does not automatically mean there is a major problem with the application. The important part is understanding what the council is asking and providing a response that addresses the issue clearly.

6. Will Other People Be Involved?

Council also considers whether the application should be notified.

Depending on the proposal and the applicable legal tests, the application may be:

Non-notified: Processed without submissions from the public

Limited notified: particular affected people can make submissions

Publicly notified: The wider public has an opportunity to make submissions

Most resource consent applications are processed on a non-notified basis, but the appropriate pathway depends on the circumstances of each proposal.

Where an application is notified, additional stages can be introduced, including submissions and potentially a hearing.

7. What Happens at a Resource Consent Hearing?

Not every consent goes to a hearing.

Where a hearing is required, it provides an opportunity for the applicant and relevant submitters to present information before a decision is made.

Planning and technical specialists may prepare evidence explaining the proposal, its environmental effects and how it should be assessed under the relevant planning framework.

For more complex or contested applications, this can become a significant part of the overall consent process.

8. Council Makes a Decision

At the end of the assessment, the consent authority decides whether to grant or decline the application.

If resource consent is granted, it will usually come with consent conditions.

These conditions can set requirements around how the approved development or activity is carried out. Depending on the project, they may relate to matters that need to happen:

Before work starts → during development → once work is complete → during ongoing operation

The decision and its conditions should therefore be reviewed carefully before moving into the next stage of the project.

What Happens After Resource Consent?

Resource consent is often one approval within a much wider development process.

Building consent or other approvals may still be required, and conditions attached to the resource consent may need to be satisfied at particular stages.

For the project team, the focus now shifts from getting the approval to making sure the approved development is delivered in accordance with it.

Navigating the Resource Consent Process

The consent pathway depends on the proposal, the planning rules it triggers and the environmental effects that need to be considered.

Civix's planning team can manage the process from the initial planning assessment and application preparation through to council queries, notification where applicable and the final consent decision.

Related Guides VIEW ALL

What Planning Checks Should You Make Before Buying or Developing a Site?

A property can look perfect for a development on paper. It might be in the right location, have plenty of space and appear suitable for what you have planned.

READ MORE  

How Do District Plan Rules Affect What You Can Build on a Property?

Two properties can look almost identical but have very different development potential.

READ MORE  

What Happens During the Resource Consent Process in New Zealand?

Finding out that a project needs resource consent is only the beginning.

READ MORE  

What Can Make a Development More Difficult to Consent?

Some developments move through the planning process relatively smoothly. Others require more investigation, supporting reports, consultation or changes to the design before consent can be granted.

READ MORE  

Understanding Earthworks: What Your Project May Need and How to Get Started

Earthworks are often one of the first major stages of a subdivision or land development project. They involve reshaping the existing ground so the site can support buildings, accessways and other future construction.

READ MORE  

From Design to Approval: Understanding the Engineering Approval Process

Engineering approval is the stage where detailed civil plans are reviewed before construction begins. It is commonly required for subdivisions and developments involving earthworks, roads, accessways, drainage or connections to public infrastructure.

READ MORE  

Understanding Flood Risk: Overland Flow Paths, Flood Modelling and Site Constraints

Flood-related constraints can affect where buildings are placed, how high finished floor levels need to be and how stormwater is managed across a development site.

READ MORE  

Planning Safe and Practical Access: Roads, Driveways and Vehicle Movement

Access design affects how safely and easily vehicles can enter, leave and move around a property. It can also influence the wider layout of a subdivision or development, including building placement, earthworks and service connections.

READ MORE  

Site Services Explained: Water, Wastewater and Stormwater for New Developments

Site services are the systems that allow a development to connect with essential infrastructure. For most subdivision and land development projects, this includes water supply, wastewater disposal and stormwater management.

READ MORE  

Erosion & Sediment Control Guide

Earthworks can significantly change the way water moves across a development site. Once vegetation is cleared or soil is exposed, rainfall can loosen and carry sediment into stormwater networks, neighbouring properties, streams and other receiving environments.

READ MORE  

Overland Flow Paths & Flood Risk Guide

Flood risk is not always obvious when looking at a property. A site may remain dry in normal conditions but still sit within a flood-prone area or carry significant surface water during heavy rainfall.

READ MORE  

Stormwater Treatment Design Guide

Stormwater treatment is an important part of many subdivision, land development and infrastructure projects. As sites are developed, buildings, roads, car parks and other hard surfaces can increase the volume and speed of runoff while also changing the types of contaminants entering the stormwater system.

READ MORE  

On-Site Stormwater Management Guide

Development usually increases the amount of hard surface on a property. Roofs, driveways, roads and paved areas prevent rainfall from soaking naturally into the ground, which can increase the volume and speed of stormwater runoff.

READ MORE  

Chemical Treatment for Earthworks Guide

Earthworks can produce sediment-laden runoff when exposed soil is disturbed by rainfall. Standard erosion and sediment controls are often used to slow this water and allow suspended soil particles to settle before discharge.

READ MORE  

Building Consent vs Resource Consent: What’s the Difference?

Building consent and resource consent are often talked about together, but they deal with different parts of a development project.